During a tumultuous 4th quarter, all banks, investors and stakeholders decided to align their...

The live fire drill was completed successfully with thanks to the voluntary fire brigade from...

The first delivery of biodiesel produced in our plant in Gaishorn has been delivered.

The railway siding has been completed at the end of April. The first delivery of oils has taken...

In the past few weeks a lot of effort was put in building the tankfarm. Also, the progress with...

In the past few weeks a lot of work was done for the railway connection. Construction progresses...

There has been a lot of progress during the past few weeks at the construction site in...

In October/November 2007 the steam connection bridge to the adjacent biomass plant was built. The...

During the summer months they started to install the basic equipment and machinery.

In June the walls and the cladding of the production facility were put up. Also the construction...

Construction for the plant is in full swing. The fundament plate is ready and the steel...

The official groundbreaking ceremony to launch the construction for the biodiesel plant in...